Vattenfall and TenneT have signed agreements for the Hollandse Kust Zuid offshore grid connection

Grid operator TenneT and wind farm developer Vattenfall have signed agreements for the construction of an offshore grid connection for the Hollandse Kust Zuid I and II wind farms. The agreements concern the realisation of the connection and the transmission of electricity between the 700 MW wind farm of Vattenfall and the TenneT Hollandse Kust Zuid Alpha offshore platform.

TenneT’s offshore transformer platform (artist’s impression) (Courtesy of Vattenfall Aktiebolag)

Vattenfall won this first subsidy free public tender issued by the Dutch government in March 2018.

Marco Kuijpers, Senior Manager Offshore Nederland at TenneT: ‘This agreement is another fantastic step towards making the Dutch electricity system sustainable. The sea grid is now really taking shape, first with 1,400 MW in the Borssele wind area, followed by Hollandse Kust Zuid and finally Hollandse Kust Noord in 2023. In the meantime, we’re preparing for the next North Sea projects in consultation with the Ministry of Economic Affairs & Climate.’

'This is a big milestone for the project and we’re glad that it is advancing well’, says Gunnar Groebler, Head of BU Wind and member of the EGM of Vattenfall. Contracts are signed well ahead of the deadline in March this year. We are looking forward to continue our cooperation with TenneT and materialize this project as a big contribution to the Dutch energy transition.’

Offshore grid: Hollandse Kust Zuid

Hollandse Kust Zuid offshore grid comprises two transformer platforms at sea, each with a 700 megawatt capacity, two 220 kV alternating current cables per platform, a yet-to-be-constructed onshore substation and an expansion of the existing ‘De Maasvlakte’ onshore high voltage substation where wind power from the sea is connected to TenneT’s Randstad 380 kV Zuidring. The wind power will be supplied to electricity consumers across the country via the national high voltage grid.

TenneT has been officially designated by the Dutch government as offshore grid operator. TenneT is realising grid connections at sea with a total capacity of at least 3,500 MW, in accordance with a standardised concept of 700 MW per grid connection. The two connections from the Hollandse Kust Zuid offshore grid, which have a joint capacity of 1,400 MW, will become operational a year apart, in 2021 and 2022, in accordance with the Energy Agreement.Facts and figures about Hollandse Kust Zuid I and II
  • 356 km2 in total, 22.2 km from the Dutch west coast
  • Total capacity: 700 - 750 MW
  • Sustainable electricity for 1 to 1.5 million households

References

[1]

Vattenfall Aktiebolag. Press release - Vattenfall and TenneT have signed agreements for the Hollandse Kust Zuid offshore grid connection. URL: https://group.vattenfall.com/press-and-media/news--press-releases/newsroom/2019/.... [Date Accessed: 15/01/2019].

Transmission

04 Dec | ABB commissions first digital substations in Italy

ABB Ability™ based technology to boost efficiency and enable supply of clean wind energy

Transmission

18 Sep | Balfour Beatty innovation puts connections in pole position

Scottish and Southern Electricity Networks (SSEN) and Balfour Beatty have successfully energised the connection for Dorenell wind farm in Moray. The wind farm connection, which will add capacity for a further 220 MW of renewable energy to the GB transmission system, has seen the deployment of composite poles, the first time this innovative technology has been used on the GB transmission system.

Transmission

30 May | GridLiance and Tri-County Electric Cooperative Reach Settlement with AEP on Wind Catcher Energy Connection Project

GridLiance, an independent transmission company with operations throughout the U.S., and Tri-County Electric Cooperative, Inc. (TCEC) announced today that they have signed a settlement agreement with American Electric Power Company (AEP) related to the proposed Wind Catcher Energy Connection project, a planned 2,000-megawatt wind farm.

Transmission

03 Apr | Vestas award Roan Wind Farm contract to DELPRO Wind

DELPRO Wind has been chosen by Vestas as HV Installation partner for Norwegian onshore project Roan wind farm, which is the first part of the very large Fosen wind farm.

Business & Finance

24 Oct | Vattenfall acquires another wind power project

Vattenfall has acquired the Vargträsk wind power project in Åsele and Lycksele municipalities in Västerbotten county. The project encompasses up to 21 wind turbines and has the potential to generate renewable energy for around 50,000 homes. The plan is for the wind power plant to be operational in 2021-2022.

Operation & Maintenance

26 Sep | Vattenfall and Aquila Capital sign long-term deals for new wind power in Sweden

Vattenfall and German-based Aquila Capital have signed 15 year agreements for wind power and balancing services for the wind farm Kråktorpet (163 MW) in northern Sweden.

Project Development & Execution

31 Aug | Updated plans for north east wind farm on show

Vattenfall, the Swedish energy group, is seeking feedback from local residents and businesses on updated wind farm proposals near Huntly in Aberdeenshire, the developer said today [Friday 31 August].

Business & Finance

23 May | Vattenfall and Facebook sign long-term deals for new Nordic renewable energy

Vattenfall and Facebook have signed long-term supply and service agreements for integrating the output of three new Norwegian wind projects into the electric grid that provides power to Facebook’s Nordic data centres in Odense, Denmark, and Luleå in Sweden.