Reported by TenneT on 5 April 2019

TenneT connects Dutch North Sea wind farms using the world’s highest capacity connections

It was announced today that TenneT, as onshore and offshore transmission system operator, will connect 6.1 gigawatts of new offshore wind farms to the Dutch high voltage grid between 2024 and 2030. TenneT will be using cost-efficient and future-proof technologies for this and the surroundings and environment will be spared as much as possible during construction.

(Courtesy of TenneT Holding B.V.)

ul class="arrows">
  • Global innovations for IJmuiden Ver wind area
  • For the first time 2 gigawatt converterstations and cables will connect offshore wind energy 
  • Better for the environment and reduces costs
  • Manon van Beek, CEO TenneT: ‘In doing this we are making an important contribution to accelerating the energy transition. Based on our experiences with innovative technology in Germany, we can now help realise Dutch ambitions for the development of offshore wind power with fewer cables, fewer platforms and with less spatial impact and less disturbance to the surroundings and the environment both at sea and on land.’

    With his letter to the Lower House of Parliament, the Minister of Economic Affairs & Climate (EZK) took an important step today in implementing the roadmap for the development of offshore wind energy up to 2030. EZK has given TenneT the responsibility to connect a total of 9.6 GW . 5.6 GW of this will be connected to alternating current (AC) connections and 4 GW to innovative direct current (DC) connections. Together with the already operational offshore wind farms, the offshore wind power capacity will reach 10.6 GW by 2030. This is equivalent to almost 22 times the capacity of the Borssele nuclear plant.

    World first with 2-gigawatt capacity

    The wind power areas Hollandse Kust (west) and Ten Noorden van de Waddeneilanden will benefit from TenneT’s standardised AC-concept with offshore electrical substations of 700 MW. These pool the electricity from the wind farms. 220-kV cables then transport the wind electricity to the coast.

    In the IJmuiden Ver offshore wind energy area, two direct current connections (comprising cables and converter stations) will be used; for the first time in the world with a 2,000 MW (2GW) capacity. The cables will have a 525 kV (525,000 V) voltage level. This makes optimum use of the area's scale and also corresponds with the wind industry wishes for larger wind farms. For a larger capacity of 2 gigawatt, just two instead of six cables are needed (lower costs) and this also takes up less space. Fewer routes will be required onshore and therefore the environment will be spared as much as possible.


    Artist impression of a 2GW offshore converter platform for IJmuiden Ver

    Significant benefits gained from German activities

    The step to realising 2 GW power connections is possible because of TenneT’s unique experience with HVDC  network connections in Germany. There, TenneT is connecting large-scale offshore wind farms based on direct current. Direct current cables of 2 GW on land also form the basis for the yet-to-be-constructed SuedLink and SuedOstLink . TenneT is using the high voltage level of 525 kV for the new international connection between Germany and Norway, NordLink.

    In connecting the wind farms at IJmuiden Ver, two 2 GW offshore converter stations will be constructed to convert the alternating current generated by the wind farms into direct current. This technology prevents transmission losses. On land, converters will then convert the direct current into alternating current for further transmission and distribution to companies and households. Connecting to the most sensible points in the grid can also prevent large investments in the national high voltage grid. The offshore converters and wind turbines at IJmuiden Ver (approx 80 km off the coast) will not be visible from land.

    TenneT continues to innovate

    As well as this innovative connection concept, TenneT is taking its responsibility as offshore transmission operator by working on solutions to utilise the infrastructure more efficiently. In that light, TenneT is investigating, together with the gas sector and in consultation with the Ministry of EZK, whether the energy needs of offshore gas platforms can be provided with sustainable electricity via a connection to the offshore grid. A connection from IJmuiden Ver with the United Kingdom that can also be used as interconnection (WindConnector) when there is less wind can contribute to a more efficient use of the infrastructure.

    Offshore wind power as the basis for energy transition

    According to TenneT, offshore wind power is essential for our energy transition. Manon van Beek: ‘It not only provides us with a lot of sustainable electricity, but in the long term it will also form an important source of green hydrogen, which will enable other sectors than the electricity sector to take the necessary step towards sustainability. This could include transport, industry, fertiliser production, shipping and aviation. Until now, it is largely an electricity transition, but all other sectors will also have to take part and we would like to help create the correct conditions.’

    3.5 GW according to Energieakkoord (up to 2023)

    Delivery Capacity Wind area Technology 2019/2020 1.4 GW Borssele 2 x 0.7 GW (AC) 2021/2022 1.4 GW Hollandse Kust (zuid) 2 x 0.7 GW (AC) 2023 0.7 GW Hollandse Kust (noord) 1 x 0.7 GW (AC)  

    6.1 GW according to Routekaart windenergie op zee 2030 

    2024/2025 1.4 GW Hollandse Kust (west) 2 x 0.7 GW (AC) 2026    0.7 GW Ten noorden van de Waddeneilanden 1 x 0.7 GW (AC) 2027/2030 4 GW IJmuiden Ver 2 x 2 GW (DC) AC = alternating current, DC = direct current

    References

    [1]

    TenneT Holding B.V. Press release - TenneT connects Dutch North Sea wind farms using the world’s highest capacity connections. URL: https://www.tennet.eu/news/detail/tennet-connects-dutch-north-sea-wind-farms-usi.... [Date Accessed: 12/04/2019].

    Transmission

    30 Jul | Steel colossus ready for transport to Borssele wind farm zone

    Load-out of first ‘jacket’ for TenneT offshore transformer platform. The 55-metre-high substructure or ‘jacket’ for TenneT’s first offshore platform in the Borssele wind farm zone has been completed. The so-called ‘load-out’ of the jacket at the HSM Offshore shipyard in Schiedam is the first milestone for TenneT in the realization of the Borssele Offshore Wind Farm Zone project.

    Transmission

    12 Jul | The North Sea "wind harvest" of the first half of 2018 exceeds the first half of 2017 by more than five percent

    TenneT sees optimisation potential through the tendering of free capacities for offshore grid connections
    • North Sea wind with 8.17 terawatt hours is stable with a strong 15 percent of total wind energy generation in Germany
    • Expansion of offshore wind farms is stagnating at previous year's level
    • TenneT is calling for western German North Sea wind farms to be linked to the Dutch electricity grid in the future.

    Transmission

    13 Jun | innogy and TenneT investigate future connection to an international Wind Power Hub

    • innogy and TenneT to jointly investigate benefits for connecting offshore wind to interconnectors across a North Sea Wind Power Hub system
    • Companies to explore the potential of connecting wind farms to an international windconnector
    • An interconnected grid system would support the deployment of larger volumes of offshore wind, strengthen European energy markets and increase security of supply across Europe

    Transmission

    13 Jun | TenneT and Vattenfall to study potential Dutch and UK offshore wind farm connections

    The benefits and feasibility of trading electricity between the UK and the Netherlands by connecting the offshore electrical infrastructure of a UK and Dutch offshore wind farm is to be assessed in a unique study by two of Europe’s major energy players, it was revealed today.