Back to top
Reported by Siemens Gamesa Renewable Energy on 24 July 2019

Siemens Gamesa signs first contract with Brennand Investimentos in Brazil for the supply of 94 MW

  • The company will install 27 SG 3.4-132 wind turbines to provide clean and affordable energy for the São Francisco River region.

  • This turbine model has received the FINAME Certificate from BNDES, qualifying it for access to the development bank's lines of financing.

(Courtesy of Siemens Gamesa Renewable Energy, S.A.)

Siemens Gamesa has signed its first contract with Brennand Investimentos to supply 27 SG 3.4-132 wind turbines for the Arizona and Honorato wind farms in Sento Sé, Bahia, with an installed capacity of 94MW. Delivery of the turbines is expected for mid-2020. *

"This is the first contract we have signed with Brennand Investimentos and we feel very proud to be considered a strategic partner for this and future projects," states Roberto Prida, Onshore Managing Director of Siemens Gamesa in Brazil. "Like Brennand Energia and Brennand Investimentos, we are committed to continue reducing the levelized cost of energy, making wind power even more affordable and efficient to meet the energy needs of the country’s Northeast Region".

The SG 3.4-132 turbine model received the BNDES FINAME Certificate in early 2019. The certification means that they meet the requirements of the development bank, providing project developers with special financing lines for the purchase of the product.

According to Mozart Siqueira, Chief Executive Officer of Brennand Investimentos, the decision to use the Siemens Gamesa SG 3.4-132 turbine to produce energy for the free market in Brazil was due to its technical characteristics, its suitability for the wind of Sento Sé and the confidence in product quality and maintenance provided by Siemens Gamesa. "We hope that the signing of this agreement will be the beginning of a long-term partnership between our companies and that the introduction of new products by Siemens Gamesa will continue with the demonstrated quality and competitiveness.

"The SG 3.4-132 onshore wind turbine is the most competitive product in its segment, featuring optimal levelized cost of energy for medium and high winds, rotor diameter of 132 meters, a flexible power rating of 3.3-3.75 MW depending on the project requirements, and low risk based on proven technologies and enhanced performance with the highest levels of reliability.

The project will add 94 MW of power to the 247.45 MW produced by Brennand Energia, a company owned by the same family group, at eight wind farms in the city of Sento Sé. The municipality lies 689 km from the capital Salvador, on the banks of the São Francisco River. Although the river is known for its hydroelectric power plants, there is a tendency for investment in wind energy, which brings the advantage of leaving the river waters available for the region's main economic activity:agriculture and farming.

Since 2012, Siemens Gamesa has provided more than 3.1 GW (more than 1,500 units) for around 60 project sites across Brazil. The company has a strong footprint in the country, including a nacelle assembly plant in Camaçari.

*The order was signed in Q3 of fiscal year 2019.

References

[1]

Siemens Gamesa Renewable Energy, S.A. Press release - Siemens Gamesa signs first contract with Brennand Investimentos in Brazil for the supply of 94 MW. URL: https://www.siemensgamesa.com/en-int/newsroom/2019/07/190724-siemens-gamesa-onsh.... [Date Accessed: 24/07/2019].

Technology

14 Dec | Siemens Gamesa and Aalborg University to lead EU-funded R&D project to make offshore wind one of the most affordable energy sources

  • i4Offshore project to receive almost 20 million euro in support over five-year duration
  • Goal is to deliver offshore wind solutions making consumers' electricity bills both lower and greener compared to fossil fuel or other renewable energy sources
  • Technologies tested to include 1,000-ton bucket foundation, steel jacket, a concrete transition piece, new cable connection
  • 15 project partners companies include experts from all fields within the offshore wind industry; one of the largest offshore wind energy R&D projects ever
  • Official title: "Integrated Implementation of Industrial Innovations for Offshore Wind Cost Reduction"

Order

03 Dec | Siemens Gamesa to supply 487 MW SeaMade offshore wind power project in Belgium

  • Project to utilize 58 SG 8.0-167 DD offshore wind turbines; 17-year Long Term Service agreement with logistics included
  • SeaMade is the name of two combined offshore wind projects, previously known as Mermaid (235 MW) and Seastar (252 MW)
  • Clean energy to be provided to 485,000 households
  • Installation and commissioning expected to be completed before the end of 2020

Order

22 Oct | Siemens Gamesa named preferred supplier for Ørsted’s 900 MW Greater Changhua offshore wind power projects in Taiwan

  • 900 MW projects to utilize approx. 112 SG 8.0-167 DD offshore wind turbines; Service agreement included
  • Subject to final contract, Siemens Gamesa will establish a nacelle assembly facility near Taichung Harbor for start of production in 2021, going beyond the localisation requirements
  • Local tower supply set-up through CS Wind and Chin-Fong partnership to be used
  • Offshore construction for the projects to begin in 2021

03 Oct | Siemens Gamesa awards first two contracts for localized offshore wind turbine components in Taiwan

  • Swancor to supply resin for Formosa 1 Phase 2 blades
  • Collaboration between CS Wind and Chin Fong Machine Industrial to supply 100% localized towers required for wpd’s Yunlin project in 2021
  • SGRE prepared to fulfil future local content requirements