Reported by Siemens Gamesa Renewable Energy on 2 July 2019

Siemens Gamesa awarded the largest repowering order to date in North America by MidAmerican Energy

  • The company will supply and install 163 SG 2.7-129 wind turbines, operating at 2.38 MW and 18 previously sold SWT-2.3-108 wind turbines to repower the Rolling Hills wind project (429.3 MW), with an option for 12 additional wind turbines
  • The nacelles and hubs will come from Hutchinson, Kansas nacelle and hub assembly facility and blades will come from Fort Madison, Iowa blade manufacturing facility

(Courtesy of Siemens Gamesa Renewable Energy, S.A.)

Siemens Gamesa has been selected by MidAmerican Energy Company for the Rolling Hills wind power project for a total of 429.3 MW, the largest repowering order to date in North America. The company will repower the project with 163 SG 2.7-129 and 18 previously sold SWT-2.3-108 wind turbines.

Rolling Hills is located in Adair, Adams and Cass counties in Iowa and currently features 193 SWT-2.3-101 turbines. The repowering project includes replacement of the blades, hubs and nacelles for all units, and top tower sections for the SG 2.7-129 units. Commissioning of the project is expected for late 2021.

The SG 2.7-129 turbine builds on the robust and successful 2.3-MW geared product series.

“We are excited to provide upgraded equipment and technology to the Rolling Hills project in Iowa, a national leader in the wind energy industry. This new project is a testament to MidAmerican Energy’s confidence in us as well as Iowa, where we have supplied them with more than 2.6 GW,” stated José Antonio Miranda, CEO of Onshore Americas at Siemens Gamesa Renewable Energy. “The blades will be produced right there in Iowa and the nacelles and hubs will come from neighboring Kansas, making this a truly local project.”

Siemens Gamesa has installed more than 10,000 wind turbines in the U.S. totalling approximately 20 GW of installed capacity. In Iowa, Siemens Gamesa has installed nearly 1,400 wind turbines for a total of almost 3.5 GW. The company has a strong footprint consisting of service, offices and two manufacturing facilities located in Fort Madison, Iowa, and Hutchinson, Kansas.

References

[1]

Siemens Gamesa Renewable Energy, S.A. Press release - Siemens Gamesa awarded the largest repowering order to date in North America by MidAmerican Energy. URL: https://www.siemensgamesa.com/en-int/newsroom/2019/07/190702-siemens-gamesa-onsh.... [Date Accessed: 03/07/2019].

Technology

14 Dec | Siemens Gamesa and Aalborg University to lead EU-funded R&D project to make offshore wind one of the most affordable energy sources

  • i4Offshore project to receive almost 20 million euro in support over five-year duration
  • Goal is to deliver offshore wind solutions making consumers' electricity bills both lower and greener compared to fossil fuel or other renewable energy sources
  • Technologies tested to include 1,000-ton bucket foundation, steel jacket, a concrete transition piece, new cable connection
  • 15 project partners companies include experts from all fields within the offshore wind industry; one of the largest offshore wind energy R&D projects ever
  • Official title: "Integrated Implementation of Industrial Innovations for Offshore Wind Cost Reduction"

Order

03 Dec | Siemens Gamesa to supply 487 MW SeaMade offshore wind power project in Belgium

  • Project to utilize 58 SG 8.0-167 DD offshore wind turbines; 17-year Long Term Service agreement with logistics included
  • SeaMade is the name of two combined offshore wind projects, previously known as Mermaid (235 MW) and Seastar (252 MW)
  • Clean energy to be provided to 485,000 households
  • Installation and commissioning expected to be completed before the end of 2020

Order

22 Oct | Siemens Gamesa named preferred supplier for Ørsted’s 900 MW Greater Changhua offshore wind power projects in Taiwan

  • 900 MW projects to utilize approx. 112 SG 8.0-167 DD offshore wind turbines; Service agreement included
  • Subject to final contract, Siemens Gamesa will establish a nacelle assembly facility near Taichung Harbor for start of production in 2021, going beyond the localisation requirements
  • Local tower supply set-up through CS Wind and Chin-Fong partnership to be used
  • Offshore construction for the projects to begin in 2021

03 Oct | Siemens Gamesa awards first two contracts for localized offshore wind turbine components in Taiwan

  • Swancor to supply resin for Formosa 1 Phase 2 blades
  • Collaboration between CS Wind and Chin Fong Machine Industrial to supply 100% localized towers required for wpd’s Yunlin project in 2021
  • SGRE prepared to fulfil future local content requirements