Reported by RES on 8 November 2018

RES Complete Major Component Replacement

RES’ growing O&M team has successfully completed a major component change at Altahullion wind farm in County Derry, Northern Ireland.

RES' O&M team temporarily remove the blades of a 15-year old turbine at Aultahullion. (Courtesy of Renewable Energy Systems Limited)

In order to replace the yaw ring on the 15-year old Siemens 1.3 turbine, the RES team re-engineered a suite of heavy lifting tools and support frames.

The task, which involved the removal of the rotor and nacelle and then a rebuild of the turbine, took five days onsite and a team of six engineers.

Brian McDaid, head of turbine O&M at RES, oversaw the task. He said: “As a growing number of turbines come towards the end of their natural life, some will require major maintenance due to wear and tear, there is an opportunity for us to offer our O&M expertise to the wider market.

“For this reason we have re-engineered a suite of universal tools, including support frames for rotors and nacelles and heavy lifting brackets, or that can be used on various turbines, allowing us to offer competitive turbine repair services to asset managers and developers around the UK.

“We have already completed repairs on both Vestas and Siemens turbines, and expect demand to grow significantly over the coming years.”

References

[1]

Renewable Energy Systems Limited. Press release - RES Complete Major Component Replacement. URL: http://res.mynewsdesk.com/pressreleases/res-complete-major-component-replacement.... [Date Accessed: 08/11/2018].

Operation & Maintenance

03 Apr | Aeolus Energy Group Awards Tower Fabrication Contract to Ventower Industries

Complete Training Towers Will be Installed at New Offshore Wind Training Facility