RES’ growing O&M team has successfully completed a major component change at Altahullion wind farm in County Derry, Northern Ireland.

RES' O&M team temporarily remove the blades of a 15-year old turbine at Aultahullion. (Courtesy of Renewable Energy Systems Limited)

In order to replace the yaw ring on the 15-year old Siemens 1.3 turbine, the RES team re-engineered a suite of heavy lifting tools and support frames.

The task, which involved the removal of the rotor and nacelle and then a rebuild of the turbine, took five days onsite and a team of six engineers.

Brian McDaid, head of turbine O&M at RES, oversaw the task. He said: “As a growing number of turbines come towards the end of their natural life, some will require major maintenance due to wear and tear, there is an opportunity for us to offer our O&M expertise to the wider market.

“For this reason we have re-engineered a suite of universal tools, including support frames for rotors and nacelles and heavy lifting brackets, or that can be used on various turbines, allowing us to offer competitive turbine repair services to asset managers and developers around the UK.

“We have already completed repairs on both Vestas and Siemens turbines, and expect demand to grow significantly over the coming years.”

References

[1]

Renewable Energy Systems Limited. Press release - RES Complete Major Component Replacement. URL: http://res.mynewsdesk.com/pressreleases/res-complete-major-component-replacement.... [Date Accessed: 08/11/2018].

Operation & Maintenance

07 Jan | CEZ Relies for Wind Farm Management on wpd windmanager

New wind farm for the wpd windmanager GmbH & Co. KG: As of January 1, 2019, the CEZ Group assigns the operational management for the wind farm Fohren-Linden to the Bremen-based company.

Operation & Maintenance

28 Nov | Operational Management for Polish Wind Farm of Green Bear

Eagerly, the wind energy industry looks towards Poland. After around three years of standstill, the Polish government encourages the development of wind energy again by initiating new tenders. The results have just been published.

Operation & Maintenance

19 Nov | RES awarded Asset Management Services Contract by NTR for Castlecraig

Castlecraig Wind Farm, owned by sustainable infrastructure investors and asset managers NTR, will be operated by leading renewable energy business, RES, following the awarding of an asset management services contract.

Operation & Maintenance

01 Oct | Erova signs first Balancing Agreement ahead of the new Irish Electricity Market

Erova, an independent energy trading and services company based in Dublin with offices in London and Amsterdam, announces it has contracted with Greencoat Renewables PLC to manage the balancing requirements for two wind farms (Knockacummer and Kill Hills) as required under the new Integrated Single Electricity Market (I-SEM).

Operation & Maintenance

19 Nov | RES awarded Asset Management Services Contract by NTR for Castlecraig

Castlecraig Wind Farm, owned by sustainable infrastructure investors and asset managers NTR, will be operated by leading renewable energy business, RES, following the awarding of an asset management services contract.

Business & Finance

24 Oct | RES sells the Vargträsk wind project to Vattenfall

RES, known locally in Scandinavia as Nordisk Vindkraft, has sold the Vargträsk wind project in the County of Västerbotten, Sweden, to Vattenfall. The project consists of 21 turbines and has an installed capacity of 80MW, enough to power approximately 50 000 homes*.

Project Development & Execution

18 Oct | RES to complete its first repowering in collaboration with the French wind turbine manufacturer POMALeitwind

Following a tender held by the French Energy Regulation Commission (CRE), Souleilla-Corbières wind farm has been selected for repowering.

Business & Finance

16 Oct | RES signs Utility PPAs with UNIPER on two French TRIG-owned wind farms

Optimisation of existing PPAs