Reported by Quinbrook Infrastructure Partners on 11 September 2018

Quinbrook Commences Operations at $270 Million USD Persimmon Creek Wind Farm

  • Persimmon is the first project in the Scout Clean Energy portfolio to complete development, construction and begin operations
  • Persimmon’s construction was completed on time and on budget

(Courtesy of pixabay.com)

Quinbrook Infrastructure Partners ("Quinbrook"), a global investment manager specializing in lower carbon and renewable energy infrastructure assets, has announced the successful completion of construction and the commencement of commercial operations at the 200 megawatt (MW) Persimmon Creek wind farm in Oklahoma (“Persimmon”).

Persimmon’s construction was completed in under nine months by Wanzek Construction and utilizes 73 GE 2.5 MW turbines located across 17,000 acres in Dewey, Ellis and Woodward counties, Oklahoma. The Persimmon wind project is a joint venture between Quinbrook and Elawan Wind, USA and will be initially operated under a GE Full Service O&M Agreement.

Persimmon was financed with equity investments from both Quinbrook and Elawan along with tax equity investments from a consortium comprising of GE Energy Financial Services and J.P. Morgan. Construction lending was provided by ABN Amro, GE Energy Financial Services, MUFG and Rabobank. Persimmon will sell power into the Southern Power Pool (SPP) market under a long-dated energy hedge provided by an affiliate of Citi.

“We are delighted to have Scout’s first wind farm project up and running and to have completed construction on time and on budget. We believe that Persimmon is an outstanding wind project located in a very robust wind regime,” said Jeff Hunter, Senior Managing Director of Quinbrook. “The significant amount of tax equity financing we have secured from both GE and J.P. Morgan is testament to the quality and differentiation of the project and complements the development work undertaken by Scout’s team together with operations affiliate Harvest Energy Services and, of course, our partner Elawan. This is an important milestone for Scout, which will now assist acceleration of the remaining projects in its diverse and growing wind power portfolio which Quinbrook and the Scout team have together expanded to over 2.3GW spanning 13 projects in 10 states.”

“Persimmon’s successful completion is an important catalyst for Scout and paves the way for several additional Scout wind projects that are nearing completion of development and which are scheduled to commence construction over coming months. The Scout and Quinbrook teams worked closely with GE in late 2017 following the US tax reforms to ensure Persimmon would proceed when many other projects stalled. We acknowledge their efforts and those of our partner Elawan in successfully navigating many obstacles to get Persimmon built on time and on budget,” said Michael Rucker, Chief Executive Officer at Scout Clean Energy.

References

[1]

Quinbrook Infrastructure Partners Pty Ltd. Press release - Quinbrook Commences Operations at $270 Million USD Persimmon Creek Wind Farm. URL: https://www.quinbrook.com/single-post/2018/09/11/Quinbrook-Commences-Operations-.... [Date Accessed: 01/10/2018].

Project Development & Execution

17 Jan | Invenergy Announces Start of Commercial Operations of Upstream Wind Energy Center

Invenergy, a leading privately-held global developer and operator of sustainable energy solutions, announced today the completion of construction and the start of commercial operations of the 200-megawatt Upstream Wind Energy Center in Antelope County, Nebraska.

Project Development & Execution

15 Jan | EDF Renewables announces Commercial Operation at Copenhagen Wind farm in New York

EDF Renewables North America announced today that the 80 megawatt (MW) Copenhagen Wind Project is fully operational and delivering electricity.

Project Development & Execution

09 Jan | Capital Power continues to deliver successful contracted renewable projects

Capital Power Corporation (Capital Power or the Company) (TSX: CPX) announced its New Frontier Wind project, located in North Dakota, began commercial operation on December 21, 2018.

Project Development & Execution

17 Dec | Alliant Energy to add more renewable energy

Wisconsin customers to benefit from clean, affordable wind power

Business & Finance

17 Jan | Quinbrook Closes Financing on Ranchero Wind Farm in Texas

300MW project under construction and expected to be operational by year-end 2019

Project Development & Execution

08 Nov | Scout Clean Energy Secures Permits for US$150 Million Wind Farm in Indiana

130MW Bitter Ridge Wind Farm expected to commence operations in early 2020