Reported by DEME Group on 9 September 2019

Piling installation at Moray East offshore wind farm crosses halfway point

(Courtesy of Dredging, Environmental and Marine Engineering NV)

DEME Offshore is making strong progress on the installation of pin piles at the Moray East wind farm in the UK. Having started offshore construction works with the jack-up installation vessel ‘Apollo’ in May 2019, piling activities have now passed the halfway mark, with more than 156 pin piles out of a total of 309 installed. The piles are part of the jacket-based foundations on which the turbines will later be installed.

With meticulous engineering and planning, combined with carefully thought-out logistics operations which link onshore handling facilities at Invergordon with a spread of offshore vessels, the piling materials have been brought to site and smoothly hammered into their designated location.  A high degree of positional accuracy has been achieved through the use of DEME Offshore’s patented piling template, which integrates with the jack-up legs of ‘Apollo’.

Subject to the weather and any other operational conditions, DEME Offshore hopes to be able to complete the remaining piling operations by the end of 2019, in readiness for jacket installation works in 2020.

Bart De Poorter, General Manager at DEME Offshore, emphasises: “Crossing the halfway point is not only a major milestone for DEME Offshore, it also highlights the strength of the collaborative approach of all stakeholders involved. Such a complex and challenging project is only made possible by working closely with our local partners and suppliers. Together we have made good progress and will remain focused on a safe and timely completion of the pile installation.”

References

[1]

Dredging, Environmental and Marine Engineering NV. Press release - Piling installation at Moray East offshore wind farm crosses halfway point. URL: https://www.deme-group.com/news/piling-installation-moray-east-offshore-wind-far.... [Date Accessed: 09/09/2019].

28 Nov | DEME Offshore awarded major EPCI cable contract for the Neart na Gaoithe offshore wind farm in Scotland

DEME Offshore has been awarded a major EPCI contract for the inter-array and interconnector cables at the Neart na Gaoithe offshore wind farm in Scotland.

06 Nov | CSBC-DEME Wind Engineering (CDWE) signs contracts for the Zhong Neng offshore wind farm in Taiwan

Taiwan based CSBC-DEME Wind Engineering (CDWE) and the Zhong Neng Wind Power Corporation Preparatory Office have signed two contracts for the Zhong Neng offshore wind farm project.

21 Oct | Hai Long Offshore Wind Farm and CSBC DEME Wind Engineering (CDWE) join forces for the first large-scale Balance of Plant contract in Taiwan offshore wind

Today in Taipei, the Hai Long Offshore Wind (OFW) Project signed Taiwan’s first large-scale Balance of Plant (BOP) Preferred Supplier Agreement (PSA) with local company CSBC DEME Wind Engineering (CDWE), marking another significant milestone in realising the localisation of Taiwan’s offshore wind in

04 Oct | Turbine installation completed at Hornsea One offshore wind farm

On 3 October 2019, DEME Offshore’s ‘Sea Challenger’ and crew completed the installation of 174 SWT-7.0 MW turbines on  Hornsea One, the world’s largest offshore wind farm.