Reported by NEXANS on 16 October 2018

Nexans wins export cable contract for Belgium's Northwester 2 offshore wind farm

Nexans will supply a subsea power cable and associated accessories for the Northwester 2 offshore wind farm that will provide enough electricity to power around 220,000 Belgian homes.

Nexans Skagerrak on the Beatrice Offshore Wind farm (Courtesy of Nexans, société anonyme)

Pursuing an active exit strategy from nuclear power, the Belgian government is set to double the area of the country’s North Sea waters made available to offshore wind parks after 2020. The country already has four offshore wind parks that produce 871 MW of power and wants to increase that capacity to 2.2 GW by 2020 and to 4 GW by 2030. Leading the way in this transition is Parkwind, the Belgian company that develops, finances, builds and operates offshore wind farms. In the framework of Parkwind’s project Northwester 2, Nexans has been awarded contract to design, manufacture and test the submarine power export cable for the offshore wind farm.

The 219 MW Northwester 2 wind farm project is located 46 km offshore from Zeebrugge, a subdivision of Bruges. Comprising 23 turbines, it will be the seventh wind farm to be constructed off the Belgian coast. It will also be the first offshore wind farm to feature the world’s most powerful wind turbine - the 9.5 MW V164 turbine manufactured by MHI Vestas.

Nexans’ export cable will bring the renewable power from Northwester 2 wind farm to the Elia-owned Offshore Switch Yard (OSY) platform connected to Modular Offshore Grid (MOG). The three-core HVAC cable, rated at 220 kV, with state-of-the-art XLPE insulation will be supplied by Nexans in one length. Cable testing and termination works will then be carried out by the Nexans Norway team.

The submarine cable is to be manufactured in early 2019 in the Nexans Norway facility in Halden, Norway, while the associated accessories will be delivered by Nexans Switzerland plant located in Cortaillod, Switzerland.

The Northwester 2 wind farm is expected to make a significant contribution to Europe’s Climate and Energy Policy, saving around 500,000 tonnes of carbon per year, equivalent to the emissions of 170,000 cars.

“We are delighted to extend our relationship with Parkwind and contribute to the Northwester 2 project that will play a major role in Belgium’s energy transition. Building on the expertise and know-how demonstrated in previous projects, notably Northwind and Belwind, our goal is to deliver a state-of-the-art cable for Parkwind’s latest wind farm, further ensuring the reliability of the offshore grid.” - Vincent Dessale, Nexans Senior Executive Vice President Subsea and Land Systems Business Group

The Northwester 2 wind farm is expected to be fully operational in the first half of 2020.

References

[1]

Nexans, société anonyme. Press release - Nexans wins export cable contract for Belgium's Northwester 2 offshore wind farm. URL: https://www.nexans.com/newsroom/news/details/2018/10/Nexans-wins-export-cable-co.... [Date Accessed: 16/10/2018].

Transmission

15 Jan | Vattenfall and TenneT have signed agreements for the Hollandse Kust Zuid offshore grid connection

Grid operator TenneT and wind farm developer Vattenfall have signed agreements for the construction of an offshore grid connection for the Hollandse Kust Zuid I and II wind farms. The agreements concern the realisation of the connection and the transmission of electricity between the 700 MW wind farm of Vattenfall and the TenneT Hollandse Kust Zuid Alpha offshore platform.

Transmission

19 Dec | Smulders to build three offshore transformer modules for the Moray East wind farm

Siemens has awarded a contract for the construction of three offshore transformer modules (OTM) to Smulders. The project, situated off the Aberdeenshire coast in the North Sea, will be developed by EDP Renewables, ENGIE and Diamond Generating Europe.

Transmission

03 Dec | Green light for the construction of Seamade offshore wind farms

Tractebel is part of the Consortium that has been awarded a contract for the construction and installation of the Seamade offshore wind farms in the North Sea. The consortium will build the two high voltage substations, and their respective substructure, to be installed respectively in the Mermaid and the Seastar area.

Transmission

27 Nov | Van Oord select Tekmar for Borssele 2

Tekmar Energy are pleased to announce that international marine contractor Van Oord has selected the patented Tekmar Cable Protection System (CPS) TekLink® Mechanical Latch for the Borssele 2 (site III and IV) offshore wind farm.

Transmission

19 Nov | Nexans wins major power export cable contract for Ørsted’s Hornsea 2 wind farm

Nexans has won a contract worth over 150 million euros to help Ørsted deliver the most affordable electricity from offshore wind yet. The project covers the supply of over 200 km of the 245 kV high voltage alternating current (HVAC) subsea export cable system for the near shore section of Hornsea 2 wind farm.

Business & Finance

07 Nov | Nexans is awarded a multimillion-euro contract for Ørsted’s Borssele 1 and 2 wind farms off the Netherlands coast

Major contract for 66 kV submarine inter-array cable with associated accessories is the first to be placed under a new five-year framework agreement recently signed by Nexans and Ørsted.

Transmission

08 Oct | Nexans Wins Multimillion Euro Contract at UK’s Triton Knoll Offshore Wind Farm

  • J Murphy & Sons Limited awarded Nexans with a contract worth over €35 million, to supply the land export cable for the Triton Knoll offshore wind farm.
  • Nexans will supply cross-linked polyethylene (XLPE) insulated alternating current (AC) cables required to connect the offshore wind farm to the UK grid.
  • With a capacity of approximately 860 MW, the Triton Knoll wind farm will have the capability to supply the equivalent of over 800,000 UK households per year with renewable electricity.

Installation, Transport & Logistics

05 Apr | Beatrice Offshore Windfarm: Final Section of Nexans Power Export Cable Sails To Scotland

Project to bring power ashore from Scotland’s largest offshore windfarm has reached two important milestones: the successful on-site testing of the first 400 kV onshore cable link; the Nexans factory in Norway loading-out the final section of the offshore power export cable to the Skagerrak cable laying vessel.