GE Renewable Energy contracted wind turbine installation and service company Global Wind Service (GWS) to deliver crane and installation for the commissioning of the Čibuk 1 wind farm in Serbia. Covering 57x 2.75-120m GE wind turbines, it makes it the largest wind project in the Western Balkans.

Pre-assembly started at site in November 2017 and installation is planned to finish in the third quarter of 2018.

The Cibuk 1 wind farm is the first project in Serbia where GWS has been awarded both installation and craning. Vetroelektrane Balkana (WEBG), the project company behind Čibuk 1, is wholly owned by Tesla Wind, a 60:40 joint venture between Masdar, Abu Dhabi Future Energy Company and Čibuk Wind Holding.

“We are very pleased that GE Renewable Energy has given us this opportunity to take on more responsibility by awarding us with both installation and craning. Having the full scope within one contract will enable us to work more efficiently by means of improved planning and coordination between the two parties,” said Michael Høj Olsen, Chief Commercial Officer at GWS.

Due to expected potential in the Serbian market, and more work secured, GWS has established a local business unit in Serbia – supporting GWS business in the country for not only this, but also future projects.

“GWS has strong emphasis on continued growth and as such, Serbia which is a relatively new wind energy market is very interesting and promising for us,” said Lars Petersen, CEO and co-founder of GWS.

Serbia is a member of the European Energy Community and in the process of joining the EU. The country has committed to increase its share of renewable energy in an action plan. In terms of the electricity sector, Serbia is aiming for 500MW of wind capacity by 2020 –  wind thereby comprising 27.4% of the country’s total planned capacity of renewable energy for the electricity sector.

Image credit: GE Renewable Energy

References

[1]

Global Wind Service A/S. Press release - Global Wind Service delivering crane and installation for Čibuk 1 wind farm, Serbia. URL: http://globalwindservice.com/media/news/#100873. [Date Accessed: 01/10/2018].

Installation, Transport & Logistics

16 Jan | Peterson Offshore Passenger Terminal celebrates 100th flight

On the 3rd of January 2019 flight no 100 took off from Peterson Offshore Passenger Terminal at Zeeland Airport

Installation, Transport & Logistics

16 Jan | Attollo Offshore launches innovation incubator to continue drive of improving offshore marine operations

Attollo Offshore, a leading offshore marine operator, continues to cement its reputation for innovative thinking by announcing the launch of its Aberdeen-based innovation incubator.

Installation, Transport & Logistics

16 Jan | FairWind will collaborate with Siemens Gamesa on pre-assembly project in Taiwan

FairWind is proud to announce the signature on a Letter of Intent with Siemens Gamesa Renewable Energy (SGRE) to collaborate on the pre-assembly work for the Formosa 1 Phase 2 offshore wind power project in Taiwan.

Installation, Transport & Logistics

15 Jan | ABS Grants AIP for Neptun’s Wind Turbine Transport Vessel

ABS granted Approval in Principal (AIP) to Neptun Ship Design for its Wind Turbine Transport Vessel design, the first to support transporting parts for turbines greater than 9 Mega Watts (MW).

Technology

03 Jan | Global Wind Service as part of EUDP supported project to reduce risk and O&M costs of wind turbine blades

EUDP – The Danish Government Scheme for Energy Technology Development and Demonstration Program – has awarded financial support to the CORTIR project proposed by a partnership of 21 industry companies and 2 universities headed up by Bladena ApS.

Installation, Transport & Logistics

04 Dec | Global Wind Service secures installation and completion contract for Trianel Windpark Borkum Phase II, Germany

Jan De Nul Group has awarded Global Wind Service (GWS) with the installation and completion scope for the offshore wind farm Trianel Windpark Borkum Phase II (TWBII).

Project Development & Execution

06 Nov | Global Wind Service and MHI Vestas reaches half way point at Horns Rev 3

On November 3rd Global Wind Service (GWS) and MHI Vestas reached the halfway point at Horns Rev 3, when the installation of turbine number 25 was successfully completed by a team of skilled technicians from both companies, working from installation vessel Brave Tern.

Project Development & Execution

03 Sep | Final turbines installed ahead of schedule on Borkum Riffgrund 2

On 31 August 2018, Fred. Olsen Windcarrier’s jack-up installation vessel Bold Tern successfully installed the final turbine, completing the installation of MHI Vestas turbines at the Borkum Riffgrund 2 Offshore Wind Farm ahead of schedule. The 56 V164-8.0MW turbines will have a total output of 450MW.