Back to top
Reported by Global Wind Service on 6 November 2018

Global Wind Service and MHI Vestas reaches half way point at Horns Rev 3

(Courtesy of Global Wind Service A/S)

On November 3rd Global Wind Service (GWS) and MHI Vestas reached the halfway point at Horns Rev 3, when the installation of turbine number 25 was successfully completed by a team of skilled technicians from both companies, working from installation vessel Brave Tern. Work commenced at site in July.

GWS has been contracted by MHI Vestas Offshore Wind for the Installation as well as Mechanical and Electrical Completion scope.

The wind farm owned by Vattenfall stretches is established within an 88 square kilometre area, 29-44 kilometres west of Houstrup Strand on the Danish West Coast. It consists of 49 x V164-8.3 MW turbines delivered by MHI Vestas. The turbines have an impressive total height (including blade) of 187.1m, which is almost the length of two football fields. Once in operation the wind farm is expected power around 425,000 households with green energy.

References

[1]

Global Wind Service A/S. Press release - Global Wind Service and MHI Vestas reaches half way point at Horns Rev 3. URL: http://globalwindservice.com/media/news/#101073. [Date Accessed: 06/11/2018].

Project Development & Execution

11 Jan | PKN ORLEN a step closer to building an off-shore wind farm in the Baltic Sea

An ORLEN Group company Baltic Power is about to commence surveys to assess the environmental impacts and wind conditions within its off-shore wind farm licence area in the Baltic Sea. To that end, an agreement was signed with a consortium comprising MEWO S.A. and the Maritime Institute of Gdańsk, with a view to obtaining an environmental permit for the project and determining the production potential of the planned off-shore wind farm.

Project Development & Execution

27 Dec | The first turbine is spinning at Horns Rev 3 offshore wind farm

When the Danes switched on their ovens to prepare their meals during the Christmas holidays, it was partly powered by the first electricity from Denmark's next new offshore wind farm - Horns Rev 3.

Project Development & Execution

13 Dec | Tideway completes installation of longest AC offshore wind export cable at Hornsea One in the UK

A world first and a major construction milestone was reached at Ørsted’s Hornsea Project One offshore wind farm in the UK when Tideway completed the export cable installation.

Project Development & Execution

11 Dec | Hornsea One, the biggest offshore wind farm in the world, celebrates major construction milestone

  • Longest ever AC offshore wind export cable system now installed
  • Total offshore cable length of 467 km, around the same distance from London to Newcastle
  • Manufacture and installation completed months ahead of schedule

Technology

03 Jan | Global Wind Service as part of EUDP supported project to reduce risk and O&M costs of wind turbine blades

EUDP – The Danish Government Scheme for Energy Technology Development and Demonstration Program – has awarded financial support to the CORTIR project proposed by a partnership of 21 industry companies and 2 universities headed up by Bladena ApS.

Installation, Transport & Logistics

04 Dec | Global Wind Service secures installation and completion contract for Trianel Windpark Borkum Phase II, Germany

Jan De Nul Group has awarded Global Wind Service (GWS) with the installation and completion scope for the offshore wind farm Trianel Windpark Borkum Phase II (TWBII).

Project Development & Execution

03 Sep | Final turbines installed ahead of schedule on Borkum Riffgrund 2

On 31 August 2018, Fred. Olsen Windcarrier’s jack-up installation vessel Bold Tern successfully installed the final turbine, completing the installation of MHI Vestas turbines at the Borkum Riffgrund 2 Offshore Wind Farm ahead of schedule. The 56 V164-8.0MW turbines will have a total output of 450MW.

Project Development & Execution

02 Jul | Global Wind Service crosses halfway point at Borkum Riffgrund II ahead of schedule

Saturday the 30th of June the 28th MHI Vestas 8MW turbine was installed at Borkum Riffgrund II, thereby crossing the half way milestone. Top performance from all involved parties has made it possible to install the 28 turbines almost one week ahead of schedule.