Back to top
Reported by Vattenfall on 27 December 2018

The first turbine is spinning at Horns Rev 3 offshore wind farm

When the Danes switched on their ovens to prepare their meals during the Christmas holidays, it was partly powered by the first electricity from Denmark's next new offshore wind farm - Horns Rev 3.

(Courtesy of Vattenfall Aktiebolag)

On December 23, the first wind turbine on Denmark’s largest offshore wind farm Horns Rev 3 started to supply electricity from the North Sea to the Danish electricity grid.

"This is one of the best Christmas presents one can get. We are very happy and proud that the wind farm has now started to supply electricity to the Danes. It is an important step towards a fossil-free future for both Denmark and Vattenfall," says Michael Simmelsgaard, Vattenfall's Head of Offshore Wind and Danish country manager.

When Horns Rev 3 is in full operation in first half of 2019, its 49 giant turbines will increase the annual Danish electricity generation from wind by about 12 per cent or the same amount of electricity as 425,000 Danish households use on an annual basis.

"The construction of the wind farm is a huge operation that involves many vessels and people. So, we have a great deal of focus on ensuring safety. With the first turbine in operation, we now look forward to getting the remaining turbines installed and connected to the grid. It’s a great team effort," says Martin Zappe, Project Director at Horns Rev 3.

The turbines are produced by MHI Vestas and shipped from Esbjerg.

As Denmark’s largest developer of offshore wind, Vattenfall is constructing the wind farms Vesterhav Syd & Nord in the North Sea off the Danish West Coast and Kriegers Flak in the Baltic Sea.

About the Horns Rev 3 wind farm
  • With a capacity of 406 MW and an expected annual output of 1,700 GWh, Horns Rev 3 will be able to cover the annual electricity consumption of approx. 425,000 Danish households.
  • The total height of the 8,4 MW turbines is 187 metres and they each weigh close to 1.500 tonnes including foundation.
  • The turbines rest on foundations of steel that together required more than 40,000 tonnes of steel.
  • The Horns Rev 3 wind farm is located in the North Sea 25-40 kilometres off the Danish west coast.

References

[1]

Vattenfall Aktiebolag. Press release - The first turbine is spinning at Horns Rev 3 offshore wind farm. URL: https://group.vattenfall.com/press-and-media/news--press-releases/newsroom/2018/.... [Date Accessed: 27/12/2018].

Project Development & Execution

21 Jan | MHI Vestas Achieves Final Turbine Installation at Horns Reef 3

MHI Vestas Offshore Wind has installed the final turbine at Horns Reef 3 offshore wind park, now featuring the most powerful turbines in Denmark

Project Development & Execution

11 Jan | PKN ORLEN a step closer to building an off-shore wind farm in the Baltic Sea

An ORLEN Group company Baltic Power is about to commence surveys to assess the environmental impacts and wind conditions within its off-shore wind farm licence area in the Baltic Sea. To that end, an agreement was signed with a consortium comprising MEWO S.A. and the Maritime Institute of Gdańsk, with a view to obtaining an environmental permit for the project and determining the production potential of the planned off-shore wind farm.

Project Development & Execution

13 Dec | Tideway completes installation of longest AC offshore wind export cable at Hornsea One in the UK

A world first and a major construction milestone was reached at Ørsted’s Hornsea Project One offshore wind farm in the UK when Tideway completed the export cable installation.

Project Development & Execution

11 Dec | Hornsea One, the biggest offshore wind farm in the world, celebrates major construction milestone

  • Longest ever AC offshore wind export cable system now installed
  • Total offshore cable length of 467 km, around the same distance from London to Newcastle
  • Manufacture and installation completed months ahead of schedule

Transmission

15 Jan | Vattenfall and TenneT have signed agreements for the Hollandse Kust Zuid offshore grid connection

Grid operator TenneT and wind farm developer Vattenfall have signed agreements for the construction of an offshore grid connection for the Hollandse Kust Zuid I and II wind farms. The agreements concern the realisation of the connection and the transmission of electricity between the 700 MW wind farm of Vattenfall and the TenneT Hollandse Kust Zuid Alpha offshore platform.

Health, Safety & Environment

15 Nov | Will the secrets of Doggerland be revealed by unique find at North Sea site?

Archaeologists analyse pre-historic seabed evidence recovered from offshore wind farm development area

Health, Safety & Environment

01 Nov | First of kind bird study at offshore wind farm

Vattenfall calls on ornithologists to bid for research funding on Aberdeen project 

16 Oct | Vesterhav Syd and Nord will strengthen the electricity grid in West Denmark

Vattenfall's two new offshore wind farms, Vesterhav Syd and Vesterhav Nord, will be the first in Denmark to be directly involved in stabilising the electricity grid and thus the power supply.