Reported by Ørsted on 2 January 2019

Establishment permit and power purchase agreement delayed on Taiwanese offshore wind projects

Construction of Gode Wind (Courtesy of Ørsted A/S)

In April 2018, Taiwan’s Ministry of Economic Affairs awarded Ørsted the right to install 900MW offshore wind from its Changhua 1 and 2a projects in 2021.
In accordance with Taiwan Civil Code, the deadline for signing the 2018 power purchase agreement (PPA) was extended to 2 January 2019. As Taiwan’s Bureau of Energy has not issued an establishment permit for the projects by close of business local time, it is no longer possible for Ørsted and the Taiwanese utility Taipower to sign a 2018 PPA for Changhua 1 and 2a.

The 2019 feed-in-tariff has not been decided yet. However, in November 2018 the Taiwanese government proposed a 2019 feed-in-tariff of TWD5,106 (approx. EUR145) per MWh and suggested a production cap of 3,600 annual full-load hours.

Martin Neubert, CEO, Ørsted Offshore, says:

“We’re disappointed with the process and the delay of the establishment permit and PPA. We will now pause and revisit all our project activities, the timeline of the projects, and our supply chain commitments and contracts as we had assumed signing of the PPA in 2018. We’re very concerned about the suggested feed-in-tariff level for 2019 as well as the newly proposed cap on annual full-load hours. We will need to see significant changes to these proposals before we can progress any further towards a final investment decision on the projects.”

The feed-in-tariff needs to reflect the extraordinarily high costs faced by Greater Changhua 1 and 2a, mainly related to creating a local supply chain at scale, reinforcing the onshore grid infrastructure and building, operating and maintaining offshore wind farms in challenging waters where typhoons and earthquakes occur.

“The proposed retrospective changes would jeopardise the creation of a local offshore wind supply chain, harm the planned transition to renewable energy and cause significant uncertainty among international investors looking to Taiwan. Only with a stable and predictable policy framework, Taiwan has the potential for developing large-scale clean power production while creating thousands of local jobs and becoming a hub for offshore wind in Asia-Pacific,” says Martin Neubert.

The information provided in this announcement does not change Ørsted’s previous financial guidance for the financial year of 2018 or the announced expected investment level for 2018.

About Ørsted in Taiwan
  • In April 2018, Taiwan awarded Ørsted the right to connect 900MW offshore wind to Taiwan’s power grid in 2021 from Ørsted’s Greater Changhua sites.
  • In June 2018, Ørsted won the right to build an additional 920MW offshore wind capacity from its Greater Changhua sites. Subject to Ørsted’s final investment decision, these projects will be built in 2025.
  • Ørsted’s Greater Changhua projects comprise a total potential offshore wind capacity of 2.4GW. Approx 1.8GW have now been earmarked for buildout in 2021 and 2025, and the remaining approx 0.6GW can participate in future auction rounds.
  • Ørsted is also the co-owner of Taiwan’s first commercial-scale offshore wind project, Formosa 1, which will be extended from its current 8MW capacity to 128MW in 2019.
As the world leader in offshore wind, Ørsted operates more than 1,100 offshore wind turbines. Ørsted has installed approx 5.6GW offshore wind capacity and has a further 3.4GW under construction. In addition, Ørsted has secured the rights to build approx 1GW offshore wind in the US by 2023, approx 1.1GW in Germany by 2025, and approx 1.8GW in Taiwan. It is Ørsted’s ambition to have installed a total of 15GW offshore wind capacity worldwide by 2025.

References

[1]

Ørsted A/S. Press release - Establishment permit and power purchase agreement delayed on Taiwanese offshore wind projects. URL: https://orsted.com/en/Company-Announcement-List/2019/01/1866916. [Date Accessed: 02/01/2019].

[2]

Ørsted A/S. Images. https://orsted.com/en/Media/Press-kit/Images-and-logo/Images. [Date Accessed: 26/11/2018].

Business & Finance

24 Jan | EBRD supports largest windfarm in Ukraine

  • EBRD arranging syndicated loan of €150 million to SyvashEnergoProm
  • Project to be co-financed by Green for Growth Fund, FMO and NEFCO
  • EBRD’s latest investment under USELF III achieves significant CO2 reductions

Business & Finance

17 Jan | WFW advises UniCredit on Bel Lavello wind park project financing

Watson Farley & Williams (“WFW”) advised UniCredit S.p.A. (“Unicredit”) on the long-term project financing, through its Infrastructure & Power Project Finance division, of the Bel Lavello wind park, located in the southern Italian region of Basilicata.

Business & Finance

17 Jan | Quinbrook Closes Financing on Ranchero Wind Farm in Texas

300MW project under construction and expected to be operational by year-end 2019

Business & Finance

17 Jan | EDF Renewables North America Acquires Nebraska Wind Project

EDF Renewables North America has closed on a purchase agreement with York Nebraska Wind Partners, LLC, a partnership comprised of Aksamit Resource Management, LLC and York Capital Management for 100-percent of the interests in the 300 megawatt (MW) Milligan1 Wind Project located in Nebras

Project Development & Execution

30 Nov | Ørsted to build wind farm in Texas

Lincoln Clean Energy (LCE), a North American leading developer of wind and solar energy projects, will start building its first project under new Ørsted ownership – the Locket Wind project in Texas. The wind farm will be LCE’s fourth onshore

Business & Finance

09 Aug | Ørsted acquires Lincoln Clean Energy, a US onshore wind developer

Today, Ørsted has entered into an agreement with global infrastructure investment manager I Squared Capital and management shareholders to acquire a 100% equity interest in Lincoln Clean Energy LLC (’LCE’), placing an enterprise valuation on LCE of USD 580 million.