Back to top
Reported by 50Hertz Transmission on 8 November 2018

Combined Grid Solution: Successful test of Offshore cable in the Baltic Sea

The Kriegers Flak – Combined Grid Solution has reached another important milestone: Yesterday, German 50Hertz and Danish Energinet have successfully accomplished the 24 hours tests of both of the offshore cables connecting the Danish platform of the Kriegers Flak windpark with the German platform Baltic 2. One after another, the two cables „150-kV-line KFE-BaZ 155“ und „150-kV-line KFE-BaZ 156“ were energised and are now ready to transport the electricity.

(Courtesy of 50Hertz Transmission GmbH)

“Everyone in the team, from NKT, our colleagues from the Regional Center North, the platform operator EnBW and the Danish TSO ENERGINET, worked closely together and delivered to-the-point. We are very happy and celebrate this success together.”, said Sebastian Wagner, Sub-Project Manager Sea cables 50Hertz.

The Kriegers Flak – Combined Grid Solution (CGS) project will establish the world’s first offshore interconnection by linking the Danish and the German transmission grids in combination with the infrastructure of offshore wind farm grid connections.

The European Commission has designated the interconnection as a Project of Common Interest (PCI). Additionally, the interconnector project is subsidised by the European Energy Programme for Recovery.

References

[1]

50Hertz Transmission GmbH. Press release - Combined Grid Solution: Successful test of Offshore cable in the Baltic Sea. URL: https://www.50hertz.com/en/News/FullarticleNewsof50Hertz/id/5887. [Date Accessed: 12/11/2018].

Transmission

15 Jan | Vattenfall and TenneT have signed agreements for the Hollandse Kust Zuid offshore grid connection

Grid operator TenneT and wind farm developer Vattenfall have signed agreements for the construction of an offshore grid connection for the Hollandse Kust Zuid I and II wind farms. The agreements concern the realisation of the connection and the transmission of electricity between the 700 MW wind farm of Vattenfall and the TenneT Hollandse Kust Zuid Alpha offshore platform.

Transmission

19 Dec | Smulders to build three offshore transformer modules for the Moray East wind farm

Siemens has awarded a contract for the construction of three offshore transformer modules (OTM) to Smulders. The project, situated off the Aberdeenshire coast in the North Sea, will be developed by EDP Renewables, ENGIE and Diamond Generating Europe.

Transmission

03 Dec | Green light for the construction of Seamade offshore wind farms

Tractebel is part of the Consortium that has been awarded a contract for the construction and installation of the Seamade offshore wind farms in the North Sea. The consortium will build the two high voltage substations, and their respective substructure, to be installed respectively in the Mermaid and the Seastar area.

Transmission

27 Nov | Van Oord select Tekmar for Borssele 2

Tekmar Energy are pleased to announce that international marine contractor Van Oord has selected the patented Tekmar Cable Protection System (CPS) TekLink® Mechanical Latch for the Borssele 2 (site III and IV) offshore wind farm.

Transmission

05 Oct | Few months delay in the construction of converter Station in Bentwisch

Danish Energinet and German 50Hertz establish the world’s first offshore interconnection by using the national grid connections to offshore wind-farms in the Baltic Sea.

Transmission

06 Jul | Submarine Cable for Offshore-Interconnector installed

Milestone reached by linking the Danish and the German transmission grids