Reported by Capital Power Corporation on 9 January 2019

Capital Power continues to deliver successful contracted renewable projects

K2 Wind (Courtesy of Capital Power Corporation)

Capital Power Corporation (Capital Power or the Company) (TSX: CPX) announced its New Frontier Wind project, located in North Dakota, began commercial operation on December 21, 2018. The construction of the 99 megawatt facility was completed on-schedule and below its original project cost estimate of approximately $182 million (US$145 million).

On December 31, 2018 Capital Power received approximately $125 million (US$92 million) in net tax equity financing from J.P. Morgan in exchange for Class A interests of a subsidiary of the Company.

Capital Power will operate New Frontier Wind under a 12-year fixed price contract with an investment grade U.S. financial institution covering 87% of the facility’s output. Under the contract, Capital Power will swap the market revenue from a fixed volume of New Frontier Wind’s generation for a fixed price payment over a 12-year term.

“Utilizing our in-house construction capabilities, the construction of New Frontier Wind was completed in eight months and is another successful renewable development project in the United States,” said Brian Vaasjo, President and CEO of Capital Power. “With everything in place and completion below budget, New Frontier Wind is set to exceed our original return expectations.”

References

[1]

Capital Power Corporation. Press release - Capital Power continues to deliver successful contracted renewable projects. URL: https://globenewswire.com/news-release/2019/01/09/1682790/0/en/Capital-Power-con.... [Date Accessed: 09/01/2019].

Project Development & Execution

17 Jan | ACCIONA completely renovated wind farm service Spain

  • El Cabrito, located at Tarifa (Cadiz), goes from ninety 330-kW wind turbines installed in 1995 to twelve 3-MW and 1.5-MW machines of Nordex technology
  • The installation will produce 16% more clean energy with the same capacity (30 MW) as the obsolete wind farm
  • The renewal has reduced its environmental impact, as well as its visual and noise profile, and makes it easier for birdlife to fly through.

Project Development & Execution

15 Jan | ERG launches two new wind farms in France totalling 31 MW - Installed power in the country exceeds 300 MW

ERG is pleased to announce the completion of the commissioning phase for Parc Eolien de la Vallée de Torfou (17.6 MW - estimated average annual output 47 GWh), a wind farm forming part of the 768 MW of assets under construction and being developed by Epuron, acquired last year (see Press Release dat

Project Development & Execution

09 Jan | Swedish wind farm Anneberg completed and handed over to KGAL

Eolus has completed wind farm Anneberg in Tidaholm municipality in accordance with the time table set. All conditions for the completion of the transaction between Eolus and KGAL regarding the sale of the wind farm comprising 11 MW have been fulfilled and the buyer has taken over the facility.

Project Development & Execution

08 Jan | Nexans completes high voltage cable project to connect Kype Muir wind farm to Scotland’s power grid

The Scottish Government has set an ambitious target for renewable energy resources to meet 100 percent of the country’s gross annual electricity consumption by 2020. Large onshore wind farms will play a key role in meeting this target, such as the 88 megawatt (MW) Kype Muir wind farm, where Nexans has just completed a project to provide a 16 km 132 kilovolt (kV) underground grid connection for SP Energy Networks.