Reported by The Brattle Group on 31 May 2018

Brattle Analysis: 8,000 MW to 24,000 MW of U.S. Offshore Wind Proposals will Require up to 3,000 Miles of Offshore Transmission

An analysis of U.S. offshore wind developments by Brattle economists shows that state policymakers in the northeastern U.S. are now committed to procure approximately 8,000 MW of offshore wind generation over the next decade.

(Courtesy of The Brattle Group, Inc.)

In total, U.S. wind developers have proposed over 24,000 MW of offshore wind plants, of which approximately 15,000 MW involves projects that have acquired rights to the necessary offshore sites. While this scale of proposed offshore wind generation is still modest compared to global offshore development efforts, it will likely be sufficiently large to stimulate local manufacturing of offshore wind generation components and development of the necessary deployment infrastructure.

“Most of the proposed offshore wind developments will require 30 to 60 miles of offshore transmission to reach the shore,” noted Brattle Principal Johannes Pfeifenberger, a co-author of the study. “If constructed as generation tie lines to individual wind farms, 20 individual transmission lines (each able to serve a 400 MW wind plant) would be needed to interconnect the 8,000 MW of committed offshore wind developments. Our analysis shows that, at this scale of offshore wind development, the development of offshore transmission grids that can interconnect multiple wind plants can offer significant advantages over reliance on individual generation tie lines.”

The advantages of offshore grids to integrate the large scale of proposed wind developments include:
  • Lower cost due to scale economics
  • Improved use of right-of-ways and lower environmental impacts due to fewer landing points that disturb coast lines
  • Increased redundancy for delivering offshore wind generation
  • The ability to reinforce the onshore grid with the offshore transmission network
  • Open access to enable more competition between wind developers
  • Ability to introduce competition among experienced transmission developers
The study, “U.S. Offshore Wind Generation and Transmission Needs,” is co-authored by Brattle Principals Johannes Pfeifenberger and Judy Chang, with Research Analyst Daniel Jang, and is available here.

References

[1]

The Brattle Group, Inc. Press release - Brattle Analysis: 8,000 MW to 24,000 MW of U.S. Offshore Wind Proposals will Require up to 3,000 Miles of Offshore Transmission. URL: http://www.brattle.com/news-and-knowledge/news/brattle-analysis-8000-mw-to-24000.... [Date Accessed: 01/10/2018].

Transmission

15 Jan | Vattenfall and TenneT have signed agreements for the Hollandse Kust Zuid offshore grid connection

Grid operator TenneT and wind farm developer Vattenfall have signed agreements for the construction of an offshore grid connection for the Hollandse Kust Zuid I and II wind farms. The agreements concern the realisation of the connection and the transmission of electricity between the 700 MW wind farm of Vattenfall and the TenneT Hollandse Kust Zuid Alpha offshore platform.

Transmission

19 Dec | Smulders to build three offshore transformer modules for the Moray East wind farm

Siemens has awarded a contract for the construction of three offshore transformer modules (OTM) to Smulders. The project, situated off the Aberdeenshire coast in the North Sea, will be developed by EDP Renewables, ENGIE and Diamond Generating Europe.

Transmission

03 Dec | Green light for the construction of Seamade offshore wind farms

Tractebel is part of the Consortium that has been awarded a contract for the construction and installation of the Seamade offshore wind farms in the North Sea. The consortium will build the two high voltage substations, and their respective substructure, to be installed respectively in the Mermaid and the Seastar area.

Transmission

27 Nov | Van Oord select Tekmar for Borssele 2

Tekmar Energy are pleased to announce that international marine contractor Van Oord has selected the patented Tekmar Cable Protection System (CPS) TekLink® Mechanical Latch for the Borssele 2 (site III and IV) offshore wind farm.