BorWin gamma platform topside touches down in the German North Sea

The BorWin gamma topside has been successfully installed on its jacket foundation in the German North Sea. The mammoth float-over installation procedure was safely completed yesterday afternoon.

Image courtesy of Antony Hansen (Courtesy of Petrofac Limited)

Heavy lift vessel Xiang He Kou transported the 18,000 tonne platform topside to our installation site nearly 130 kilometres off the German coast from Dubai shipyard Drydocks World. The vessel completed its voyage arriving on site last weekend, having set off from the Middle East in early September.

Commenting on the completion of this major milestone, Roberto Cecchini, Project Director said: “I am delighted that the topside has been safely installed at its home in the North Sea. This is a major accomplishment and something that the various parties involved should be very proud of, specifically our client TenneT and consortium partner Siemens. The focus remains on safe and efficient delivery to complete the project in 2019.”

Petrofac, in consortium with Siemens, were awarded the BorWin3 offshore grid connection project contract in 2014 by TenneT. Scheduled to go online in 2019, the platform will house a HVDC converter station that will convert the alternating current produced by the wind turbines to direct current before transmitting it onshore to the German national grid, from where it will supply more than one million German households with clean electricity from wind power.

References

[1]

Petrofac Limited. Press release - BorWin gamma platform topside touches down in the German North Sea. URL: https://www.petrofac.com/en-gb/media/news/borwin-gamma-platform-topside-touches-.... [Date Accessed: 17/10/2018].

Transmission

04 Dec | ABB commissions first digital substations in Italy

ABB Ability™ based technology to boost efficiency and enable supply of clean wind energy

Transmission

18 Sep | Balfour Beatty innovation puts connections in pole position

Scottish and Southern Electricity Networks (SSEN) and Balfour Beatty have successfully energised the connection for Dorenell wind farm in Moray. The wind farm connection, which will add capacity for a further 220 MW of renewable energy to the GB transmission system, has seen the deployment of composite poles, the first time this innovative technology has been used on the GB transmission system.

Transmission

30 May | GridLiance and Tri-County Electric Cooperative Reach Settlement with AEP on Wind Catcher Energy Connection Project

GridLiance, an independent transmission company with operations throughout the U.S., and Tri-County Electric Cooperative, Inc. (TCEC) announced today that they have signed a settlement agreement with American Electric Power Company (AEP) related to the proposed Wind Catcher Energy Connection project, a planned 2,000-megawatt wind farm.

Transmission

03 Apr | Vestas award Roan Wind Farm contract to DELPRO Wind

DELPRO Wind has been chosen by Vestas as HV Installation partner for Norwegian onshore project Roan wind farm, which is the first part of the very large Fosen wind farm.