Reported by Oklahoma Attorney General on 7 November 2018

Attorney General Hunter Issues Update on NextEra, DOD Negotiations

Attorney General Mike Hunter today announced the deadline has been extended for NextEra and the Department of Defense (DOD) to reach a mitigation plan for a wind farm on a route airspace the military uses for training.

(Courtesy of pixabay.com)

If the FAA clears certain turbines, NextEra may proceed with construction only on those that are approved.

Construction on the company’s wind farm west of Hinton was stopped last month after NextEra and the Oklahoma Strategic Military Planning Commission (OSMPC) agreed to work on a mitigation plan with the DOD to resolve the issue. The new deadline is next Monday, Nov. 12.

The OSMPC contends the wind farm violates a recent amendment to the Wind Energy Development Act.

The changes to the law require a determination by the federal government that planned wind turbine construction has no military impact, or the company must have an approved mitigation plan from the DOD, before a wind farm is constructed or expanded.

The attorney general is representing the OSMPC in the negotiations.

References

[1]

Oklahoma Attorney General. Press release - Attorney General Hunter Issues Update on NextEra, DOD Negotiations. URL: http://www.oag.ok.gov/attorney-general-hunter-issues-update-on-nextera-dod-negot.... [Date Accessed: 07/11/2018].

Project Development & Execution

21 Jan | MHI Vestas Achieves Final Turbine Installation at Horns Reef 3

MHI Vestas Offshore Wind has installed the final turbine at Horns Reef 3 offshore wind park, now featuring the most powerful turbines in Denmark

Project Development & Execution

17 Jan | ACCIONA completely renovated wind farm service Spain

  • El Cabrito, located at Tarifa (Cadiz), goes from ninety 330-kW wind turbines installed in 1995 to twelve 3-MW and 1.5-MW machines of Nordex technology
  • The installation will produce 16% more clean energy with the same capacity (30 MW) as the obsolete wind farm
  • The renewal has reduced its environmental impact, as well as its visual and noise profile, and makes it easier for birdlife to fly through.

Project Development & Execution

17 Jan | Invenergy Announces Start of Commercial Operations of Upstream Wind Energy Center

Invenergy, a leading privately-held global developer and operator of sustainable energy solutions, announced today the completion of construction and the start of commercial operations of the 200-megawatt Upstream Wind Energy Center in Antelope County, Nebraska.

Project Development & Execution

15 Jan | ABO Wind installs 30 megawatts of wind power in Tunisia

  • Project developer obtains permission and remuneration in tender process
  • The wind farm located 35 kilometres south-east of Tunis to be commissioned in 2021

Project Development & Execution

06 Dec | NextEra, DOD Extend Deadline amid Continued Negotiations

Attorney General Mike Hunter today announced the Department of Defense (DOD) and NextEra Energy have again extended the deadline to reach a mitigation plan on a wind farm along a route of airspace the military uses for training.