Reported by Ørsted on 12 November 2018

Ørsted awards world’s largest jacket foundation contract to Sing Da Marine Structure for the first 900 MW Greater Changhua Projects

Global offshore wind leader Ørsted today signed a multi-million USD contract with Sing Da Marine Structure Corporation (SDMS), a wholly-owned subsidiary of China Steel Corporation (CSC).

(Courtesy of Ørsted A/S)

Global offshore wind leader Ørsted today signed a multi-million USD contract with Sing Da Marine Structure Corporation (SDMS), a wholly-owned subsidiary of China Steel Corporation (CSC). During 2020 and 2021 SDMS will supply 56 jacket foundations for Ørsted’s first 900MW Greater Changhua projects to be installed in 2021. This is Ørsted’s largest jacket foundation contract ever. With respect to delivery in 2020 and 2021, it is also the largest of its kind in the global offshore wind industry and demonstrates Ørsted’s strong commitment to develop Taiwan’s offshore wind supply chain.

SDMS will extend their facilities in Sing Da Harbour in Kaohsiung and have the new factory operational in the first quarter of 2020. The contract will not only give SDMS a strong pipeline, but also allow it to gain world-class knowledge and experience through working with Ørsted. The Ørsted foundation team has spent more than 18 moths to develop this partnership with CSC and SDMS and is dedicated to transferring knowledge to develop a local Taiwanese supplier for a technology area which is innovative and critical for the success of the Taiwanese offshore wind plans.

Matthias Bausenwein, Ørsted’s President for Asia Pacific, said: “Foundations are an essential part of building offshore wind power plants in Taiwan, not least due to the extraordinary demanding site conditions in the Taiwan strait. For our Greater Changhua projects, we will have to use Jacket foundations, weighing over 1,100 ton and reaching a height of approximately 75 meters. Such large structures will require outstanding fabrication performance as well as excellence in the execution phase during installation. We are very pleased to have found a strong partner who is capable of developing such skills and we look forward to executing our projects, jointly with SDMS, in a brand-new fabrication plant especially designed for manufacturing jacket foundations. Today’s contract is just a beginning of our long-term partnership since SDMS is considered as one of the preferred suppliers for our future projects which will be built in 2025”

Listed on Taiwan Stock Exchange, CSC is the largest integrated steel maker and also the leader of the national Wind team which is an alliance set up for Taiwanese suppliers to develop offshore wind business opportunities under the support of the government. Ørsted’s contract with SDMS will allow many Wind Team suppliers to join the jacket foundation sub-supply chain.

Matthias Bausenwein added, “The contract decision was made on the consideration that the two companies both have solid financial strengths, share the same business principles, and have the same dedication in developing a fully integrated local supply chain.”

The contract signed today is subject to certain conditions such as the signing of a power purchase agreement by the end 2018 and Ørsted’s final investment decision, which is expected in March 2019.

References

[1]

Ørsted A/S. Press release - Ørsted awards world’s largest jacket foundation contract to Sing Da Marine Structure for the first 900 MW Greater Changhua Projects. URL: https://orsted.tw/en/News/2018/11/sdms-foundation-contract. [Date Accessed: 12/11/2018].

Business & Finance

16 Dec | Sif to manufacture 58 monopiles for SeaMade Offshore Wind Farm

Sif Holding N.V. announces that Dredging International has awarded to Sif the production of 58 monopiles and the primary steel of the transition pieces for SeaMade offshore wind farm.

Business & Finance

14 Dec | Triton Knoll Wind Farm Earthworks

Since the official turf cutting back in September 2018, significant progress is being made on the Triton Knoll offshore wind farm project managed by lead shareholder, Innogy.

Business & Finance

12 Dec | SeaTwirls is awarded grant of €433 952 and joins alliance

SeaTwirl has joined the Ocean Energy Scale-Up Alliance (OESA) that has been granted funding from the Interreg North Sea Region.

Business & Finance

12 Dec | Attractive refinancing of the Dudgeon wind farm

The owners of the Dudgeon wind farm, Equinor, Masdar and China Resources Group, have signed a hybrid refinancing of GBP 1.4 billion. The refinancing includes commercial bank debt and senior secured notes privately placed with institutional investors.

Project Development & Execution

11 Dec | Hornsea One, the biggest offshore wind farm in the world, celebrates major construction milestone

  • Longest ever AC offshore wind export cable system now installed
  • Total offshore cable length of 467 km, around the same distance from London to Newcastle
  • Manufacture and installation completed months ahead of schedule

Business & Finance

19 Nov | Ørsted celebrates offshore wind week with successful supplier event

Ørsted, the global leader in offshore wind, is joining Renewable UK this week in celebrating the UK’s success in offshore wind.

Technology

25 Sep | Ørsted shares offshore wind farm big data with universities

Following successful data-sharing from earlier generations of offshore wind farms, Ørsted will now also share data from a wind farm featuring 6MW turbines. The aim with sharing wind farm data with technical universities is to further improve wind farm design and inspire future engineers to join the green energy industry.

Business & Finance

18 Sep | Ørsted divests 50% of Hornsea 1 Offshore Wind Farm

Ørsted has signed an agreement to sell 50% of the 1,218MW offshore wind farm Hornsea 1 to Global Infrastructure Partners (GIP). Hornsea 1 is under construction and will be the world’s largest offshore wind farm when commissioned in 2020.